Reservoir Street Sewer Extension

Update on Project (1-6--20)

Due to complications with the water table and soil conditions, CN Corp has subcontracted the final portion of the project to Walsh Contracting.  They will be performing the completion of the project over the next two weeks.  Buses and Trash Trucks will be able to pass during the construction, but the road will be closed to through traffic otherwise.  The Road will be patched for the remainder of the winter and will be scheduled to be milled and overlaid from curb to curb in the spring.

 

Thank you for your patience during the project.

 

The Town of North Attleborough Board of Public Works has contracted with CN Corp to extend the sewer on Reservoir St from Walnut St. toward Old Post Road for approximately 1,200 feet to #126 Reservoir St. 

The Project has been delayed due to unforseen conditions with the material within the trench that caused the project extend into the school season, which was not anticipated.   We are working with the contractor to detemine when the project can be done safely and not disrupt busing.

Thank you for your patience.

 

Reservoir St. Sewer Specifications

Reservoir St. Sewer Plans