95 Bridge work in Attleboro to close North Avenue 6/30/18 - 7/1/18

Traffic Cone

Please see the attached document from Mass DOT.

Estimated Start Date of Work: June 30, 2018 and July 1, 2018

Project Type: Bridge Replacement

Resident Engineer and Contact Information: Brian Lewis, Cell # 774-292-2084 

Description of Work: The contractor will be closing North Ave. under I-95 in Attleboro Saturday morning, June 30th at 6 am to begin demolition of the temporary bridge in the median of I-95.  The contractor will work through the day until 10 pm taking the bridge down.  They will leave the road closed with Police Details in place over night due to equipment and materials remaining in the road.  They will resume demolition of the bridge at 6 am on Sunday, July 1st.  The bridge is expected to be removed and the road clean and open by 6 pm Sunday night.

Contractor and Contact Information: J F White Contracting Ph. # 508-879-4700 Superintendent: Nick Bruno Cell # 617-799-2957 

Hours of Operations (Day/Night): The contractor is expected to work from 6 am to 10 pm on Saturday, June 30thth.   They will work on Sunday, July 1st from 6 am to 6 pm or until the road can be safely re-opened. 

Description of Traffic Management: Westbound traffic will be detoured right onto Stobbs Drive, then right onto Holcott Drive, then left onto North Main Street (Rte. 152), then left onto Toner Boulevard, and then left onto North Avenue.  Eastbound traffic will be diverted onto Toner Boulevard, then right onto North Main Street (Rte. 152), then Right onto Commonwealth Avenue, and then left onto North Avenue.  Both detours will be clearly signed using an approved detour plan from the contract plans. 

Estimated Duration of Work: Two days 

Additional information: Final milling and paving of I-95 SB and I-95 NB will occur during the summer.